The following is a summary and a two week look ahead for construction activity:

Above grade structural demolition of all buildings is complete. The Facades of Smith/Raskob, Reiss, Spellman and Nurses Building will remain. Construction debris continues to be removed via the east side of Seventh Avenue. Support of Excavation and Foundation is ongoing. Preparation for façade restoration is ongoing.


• Demolition on the east side of the site will be complete by the end of 2Q13

• Demolition on the west side of the site will be complete by the beginning of 3Q13

• Support of Excavation and Foundation activities will commence the end of 2Q13

• Façade restorations on 12th Street and 11th Street will commence 3Q13

• Steel erection on the east side of the site will commence 4Q13